Renovation of a residential building with 52 residential units and 2 maintenance units (2 units)
Structural work (abbreviation: VE301)- Earthwork, excavation, BK 3-4:680 m
- Waterproofing work, plinth area outer wall: 130m
- Renovation work inventory:
o Making door and window openings in MW/concrete wall: 39 pcs.
o Enlarge window openings: 60 St.
o Leveling window balustrades: 135 pcs.
o Change door lintels: 35 pcs.
o Closing old window openings: 3 pcs.
- Masonry:
o Aerated concrete: 20 m
o renovation of masonry joints
o Closing old door openings: 38 pcs.
o Crack repair
- Plastering work:
o Cleaning electric slits: approx. 2,700 m
o Complementation soffits: approx. 1,300 m
o Repair damaged plaster surfaces, 20/20 cm: approx. 550 pcs.
- Concrete renovation of arbors: approx. 350 m
- Facade scaffolding, LK4:3,000 m
- Rebuild facade scaffolding in the balcony area after dismantling: approx. 1,400 m
- insulation work (basic insulation board+slope: approx. 530 m
- Roof sealing: approx. 660 m
- Roof drains: approx. 12 pcs
- Emergency procedures: approx. 6 pcs
- Roof plumbing:
o Roof edge cover, aluminum: approx. 160 m
o Zinc downpipe: approx. 160 m
o Gutter, zinc: approx.
- trapezoidal sheet metal, balconies: approx. 40 m
- Box channel: approx. 175 m
- coating system arbors: approx. 320 m
- Safety system: approx. 28 pcs
Window (plastic) (code: VE304)- plastic windows
o Dimensions approx. 1.51/1.42 m: approx. 73 pcs.
o Dimensions approx. 2.01/1.43 m: approx. 72 pcs
o Dimensions approx. 3.45/2.46 m: approx. 54 pcs
- Apartment entrance doors approx. 1.08/2.43 m: 53 pcs.
Exterior doors (metal) (code: VE305)- Exterior doors, aluminum:
o Door element up to approx. 1.25/2.49 m: approx. 30 pcs