Estricharbeiten_Gussasphalt for the conversion and renovation of a school
As part of the renovation and partial conversion of a school building (B) from the 1970s, manufactured in large panel construction (WBS 70), not basement, 4 full floors, as well as a largely free-standing building with a swimming pool system (therapy bath), manufactured in conventional construction, basement, 1 full floor, the following construction services are awarded in public tender:
- Screed work / cast asphalt screed
The screed work / cast asphalt screed house B includes:
- Prepare 3640m2 of ground,
- Balance 910m2 of ground
- 910 m2 bituminous precoat and bitumen welding web,
- 441m2 thermal insulation D 80mm,
- 383m2 thermal insulation D 90mm,
- 72m2 thermal insulation D 100mm,
- 27m2 thermal insulation D 25mm,
- 186m2 thermal insulation D 30mm,
- 150m thermal insulation,
- 2879m2 impact sound insulation D 25mm,
- 803m2 impact sound insulation D 30mm,
- 3825m2 interface corrugated board single-layer,
- 3640m2 separating layer ribbed cardboard single-layer,
- 2005m Randdämmstreifen Rippenpappe ca. H 60mm,
- 710m Randdämmstreifen Rippenpappe ca. H 165mm,
- 71m Trennstreifen Rippenpappe ca. H 60mm,
- 25m Trennstreifen Like Rippenpappe. H165mm,
- 4 pcs cutting strips of ribbed cardboard on rising components approx. H 60mm,
- 14 pcs of cutting strips of ribbed cardboard on rising components approx. H 165mm,
- 31m Trennstreifen Anarbeiten an Fußbodenkanal,
- 90pcs connection cast asphalt penetrations approx. D 30mm,
- 5pcs connection cast asphalt penetrations approx. D 120mm,
- 2735m2 Gussasphaltestrich D 25mm,
- 262m2 Gussasphaltestrich D 30mm,
- 178m2 Gussasphaltestrich D 33mm,
- 169m2 Gussasphaltestrich D 35mm,
- 441m2 Gussasphaltestrich D 38mm,
- 31m Gussasphaltestrich anarbeiten,
- 18pcs cast asphalt screed work on floor drains, columns, inspection shaft covers approx.,
- 3640m2 surface of cast asphalt grinding, for preparation for subsequent coverings / coating