As one of two comprehensive schools in Schwerte, the Theodor Fleitmann Comprehensive School needs more classroom space based on the results of the school development plan. The additional space requirement exists on the one hand due to the formation of an upper school since the school year 2021/2022 and on the other hand due to the beginning of the 5-speed school (full operation 2024/2025).
In the run-up to the planning, a feasibility study and the so-called work phase 0 were carried out. As a result of the feasibility study and after a resolution was passed by the Schwerte City Council, a new building was to be built at the existing location.
The total space required for the new construction project is approx. 13,600 sqm GFA plus the 1-field sports hall with 700 sqm GFA.
The implementation takes place during the ongoing operation of the school. The planning and construction process should be adapted to the property conditions, taking into account the necessary interim measures. The planning should therefore also be feasible as a modular construction method if possible.
Funding according to KfW 499 is being sought for the project.
Currently, the project is expected to take about 60 months for planning and construction.
Total costs (KG 200 - 800) of approx. 63 million euros (gross) including demolition and interim measures are planned for the measure. Of this, the cost groups 300 - 400 account for approx. 44 million euros (gross).
The profitability in terms of investment and follow-up costs plays an important role.
It is planned to implement the project as a BIM project throughout.
The planning services are awarded in parallel as general planning.
The following services are to be awarded:
- Project management according to AHO (project levels 1 - 5, action areas A - E) including project management (optional)
The required services are based on the performance specifications of the AHO. The client reserves the right to commission in stages and in stages.
The client reserves the right to have the measure implemented as a modular construction (general contractor award with functional specifications).