cancellation
- Construction site equipment plus extension to KMF and Asbestos 280 StWo
- Analyses for CMF, asbestos and PCBs
- Protective layer made of one-sided coated hardboard, 7500 m²
- Dust protection wall, convertible, 1200 m²
- Implement dust protection wall, 1900 m²
- Demolition of interior walls, plasterboard, 860 m²
- Demolition of interior walls, masonry, non-load-bearing, 390 m²
- Demolition of reinforced concrete walls, non-load-bearing, 7 m³
- Demolition of reinforced concrete components, non-load-bearing, 15 m³
- Demolition of metal ceilings including substructure, 190 m²
- Demolition screed, cement screed, 170 m
- Dismantling of interior doors in metal stud walls, 170 pieces
- Removal of joint masses and removal of KMF-containing tamping compounds in the wall-ceiling connection, 500 m
- Removal of KMF-containing pipe insulation, 1050 m
- Dismantling of kitchenette furniture to varying degrees, 5 pieces
- Demolition of wall and floor tiles, 1920 m²
- Demolition of textile flooring, 4800 m²
- Demolition of elastic flooring, 740 m²
- Demolition of skirting boards, 4140 m
- Removal of permanently elastic joint compound, clearing and cleaning the component joint with asbestos-containing joint tape, 455 m
- Cleaning of floor surfaces, 9500 m²
- Cleaning of ceiling surfaces, 9500 m²
- Cleaning of wall surfaces, 15000 m²
- Residual fibre binding to surfaces, 2000 m²
- Free measurement of asbestos and KMF, 63 pieces
- Disposal of asbestos-containing and KMF-containing waste 8.0 t