Outside work
The overall performance to be provided is divided into 3 phases:
1) BA: Work on the balconies E1-E3 (EPDM coverings) from 17.4.2019 to 11.6.2019;
2) BA: Landscape work in the area of the new building from 10.6.2019 to 22.11.2019 with a planned interruption because of premeasures by the trade civil engineering.
Entrance area and playground from 10.6.2019 to 23.8.2019 Agora from 9.9.2019 to 22.11.2019;
3) BA: Work after demolition of the old building from 3.8.2020 until 18.12.2020