The subject of the assignment is the study assignment for the redevelopment of the N8 regional road in Ninove. The project area consists of the zone of the Brusselsesteenweg (kmpt. 18.95 - 21.3) with
The aim is to make it safer for traffic and to provide it with a complete cycle path infrastructure.
A preliminary design study has already been carried out for this project area. This assignment initially involves updating and reworking the existing preliminary design and the
Pre-design plans. With regard to sewerage, the design work has not yet started, so a total study of the substructure still needs to be done. The design consists of the further elaboration
From the approved preliminary design to detailed design level, both road and sewerage, together with the preparation and submission of the environmental permit file including associated procedures
(abolition of local roads, drainage invoices, groundwater modeling if necessary, [...]).
Tendering phase relates to drawing up the entire tender bundle (drawing up specifications,
Summary survey statement, estimate and final implementation plans). For the implementation, this concerns assistance and follow-up during the works. Safety coordination is not included in the assignment.
The subject of the assignment is the study assignment for the redevelopment of the N8 regional road
Ninove. The project area consists of the zone of the Brusselsesteenweg (kmpt. 18.95 - 21.3) with
The aim is to make it safer for traffic and to provide it with a complete cycle path infrastructure.
A preliminary design study has already been carried out for this project area. This contract includes in the first
Authority to update and revise where necessary the existing preliminary design and the
Pre-design plans. With regard to sewerage, the design work has not yet started and is therefore necessary
Another total study to be done of the substructure. The design consists of the further elaboration
From the approved preliminary design to the detailed design level, both road and sewerage, along with
The preparation and submission of the environmental permit file including associated procedures
(abolition of local roads, drainage invoices, groundwater modeling if necessary, [...]).
Tendering phase relates to drawing up the entire tender bundle (drawing up specifications,
Summary survey statement, estimate and final implementation plans).