The contract will be divided into two lots for the following works:
- asbestos removal of joints on existing aeronautical runways in concrete (approximately 13,000 ml);
- demolition of aeronautical runways in concrete (approximately 37,500 m
- demolition of existing infrastructure (networks, candelabra, etc.);
- creation of a provisional road serving the plots to be serviced (approximately 700 ml);
- production of connection manholes in the plots to be serviced (EP, EU, AEP, etc.)
Lot 01 - asbestos-demolitionPreparatory work - asbestos removal work on concrete paving joints - demolition work on concrete paving thickness 20 to 40 cm.
Lot 02 - VRD- Preliminary activities;
- demolition of existing networks;
- demolition work;
- Roadworks;
- sanitation works (rainwater and wastewater);
- drinking water supply works;
- telecommunications network works.