The building to be constructed is planned for use as an administrative building. In the resulting cubature, office use, including associated social, storage and technical rooms, as well as associated traffic areas are planned on 5 full and one staggered floors. In addition to the own space in the 4 lower levels, reserve space and space for external letting with administrative and commercial use are provided for the 4th floor and the second floor.
Cables and wires:
Different types of installation existing support systems, in pipe, cavity wall in wall slots
- approx. 2 500 m fire alarm cable JE-H (each) H 2 x 2 x 0.8.
central:
- 2 time recording and access terminals,
- 5-ring fire alarm computer,
- fire brigade periphery,
- burglar alarm center,
- Dialing and transmission devices.
Sensors / actuators:
- approx. 25 smoke detectors,
- approx. 30 manual call points,
- approx. 60 beeps.
Equipment:
- 100 Mifare transponders.