Lot 5 Shell construction 1st and 2nd BA concrete/timber construction
LV 04 Earthworks / Drainage BA1
specifications
1,725 cbm of excavated soil, loading and recycling/disposal
200 cbm of excavated soil, lateral storage
2,100 m² flat pit bottom, geotextile
2,685 cbm foundation cushion, ballast base course 0/45, supplying, installing, compacting DPr 1
8 St Lastplattendruckversuch (Baugrubensohle / OK Schottertragschicht)
920 cbm pipe trench excavation and excavation pits shaft, backfilling/compacting, pipeline zone gravel sand
568 m KG pipeline rainwater, DN 110 to 400, incl. bends, branches, reducers, connections
373 m KG2000 pipeline Dirty water, DN 110 to 150, incl. bends, branches, reducers, connections
15 pcs inspection shaft PVC-U, rainwater, DN 600, with 1 to 2 inlets and 1 outlet
8 pcs inspection shaft PP, dirty water, DN 600, with 0 to 2 inlets and 1 outlet