Project
Service home Tervaskanto, Somero, new building
We are requesting your contract offer for the aforementioned works according to the attached documents.
Requested unit prices are reported according to the instruction provided. The offer will be prepared on the accompanying contract offer form.
Developer
Somero City
PL 41, 31401 SOMERO
Rakennuskohde
Service house Tervaskanto, new building at Turuntie 44, 31401 Somero
Uraka Content
Construction as the main contract, according to the contract documents.
Requirements for tenders
Breakdowns and unit prices by documentation
The customer requires that the contractor has visited the site on site to explore the site.
Tervaskanto service house, new building.
at Turuntie 44, 31401 Somero.
Construction as the main contract, according to the contract documents.
2 Form of the project
2.1 Scope of performance obligation
The contract form is a shared contract. The contractor for civil engineering works acts as the main contractor and the main contractor within the meaning of the legislation. Contracts for plumbing, ventilation, building automation, sprinkler and electrical work are carried out as side contracts subordinated to the main contract.