The tender concerns the purchase and supply of polymer for sludge drainage to 5 utilities, located on Zealand and Lolland Falster. Competence Center Zealand, Guldborgsund Forsyning and Lolland Forsyning participate in the tender. Those included in the tender Utilities wish to enter into a framework agreement for the supply of polymer for pre-dewatering and final drainage to the treatment plants mentioned in this tender documents. The tender is divided into 13 lots. Please note that sludge samples must be collected in weeks 36-37.
Lot 1 Guldborgsund Wastewater: Nykøbing Falster Wastewater Treatment Plant and Marielyst Wastewater Treatment PlantGuldborgsund Wastewater: Nykøbing Falster Wastewater Treatment Plant and Marielyst Wastewater Treatment PlantTest type: First laboratory test for selection, then own performed full-scale test. The test is carried out at Nykøbing Falster wastewater treatment plant. The selected polymer will be used at both plants. The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. Only final drainage is carried out at the plant. A small amount of sludge is added to the treatment plant from trix tanks. This sludge is digested together with the rest of the sludge. 460 kg of polymer must be supplied for our own full-scale test. Minimum TS% requirement for final drainage with requirements of 20-24% TS. Minimum requirements Shrimp water quality must be observed. Here there must be a maximum of 70-100 ml of precipitate in a 1000 ml measuring cylinder glass.
Odsherred Forsyning, Fårevejle Wastewater Treatment PlantTest type: First laboratory test for selection, then own performed full-scale testThe cleaning plant is a mechanical, chemical, biologically active plant. Final drainage is carried out at the plant. Sludge from the emptying scheme is brought to the treatment plant. The plant has sludge mineralization plants, on which sludge is run from April to November. 480 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements of 19-21% TS.
Odsherred Forsyning, Nykøbing Sjælland Wastewater Treatment Plant, Final DrainageTest type As the same polymer is used for pre-drainage as for final drainage, no pre-drainage tests are required. Test type: First laboratory test for selection, then own performed full-scale test. The wastewater treatment plant is a mechanical, chemically, biologically active plant. The plant has a clarification tank and a digester. Both pre-drainage and final drainage are carried out at the plant. Sludge from the emptying scheme is brought to the treatment plant. 540 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements of 23-25% TS.
Odsherred Forsyning, Højby Wastewater Treatment Plant Test type: First laboratory test for selection, then own performed full-scale testThe cleaning plant is a mechanical, chemical, biologically active plant. Sludge thickening is carried out. Sludge from the emptying scheme is brought to the treatment plant. 155kgkg of polymer must be supplied for our own full-scale test. Minimum TS% requirement for final drainage with requirements of 20 -22% TS.
Ringsted Forsyning, Ringsted Wastewater Treatment PlantTest type: First laboratory test for selection, then own performed full-scale testThe cleaning plant is a mechanical, chemical, biologically active plant. Final drainage is carried out at the plant. 480 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements for >22% TS. Minimum requirements Shrimp water quality must be observed. Max 500 mg SS/L
Guldborgsund wastewater, Frejlev wastewater treatment plant, Engmosen wastewater treatment plant, Stubbekøbing wastewater treatment plant, Gedser wastewater treatment plant. Test type: First laboratory test for selection, then Self-performed full-scale test The test is carried out, at Frejlev wastewater treatment plant. The selected polymer will be used at all four plants. The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. Only final drainage is carried out at the plant. Surplus sludge from Krumsø Wastewater Treatment Plant (1,400 PE) is added to the inlet into the treatment plant and drained together with the plant's own sludge. 155 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements of 19 -23% TS. Minimum requirements Shrimp water quality must be observed. Here, there must be a maximum of 70-100 ml of precipitate in a 1000 ml measuring cylinder glass.
Faxe Forsyning, Haslev Wastewater Treatment Plant Test type: First laboratory test for selection, then Own performed full-scale test Haslev wastewater treatment plant is a mechanical, chemically, biologically active sludge plant, which was renovated in 2012. No surplus sludge is brought to the treatment plant from other treatment plants. The plant has sludge mineralization plants, which are overloaded. So, the screw press should relieve the beds and be used for winter driving. 125 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements of 18-20% TS. Minimum requirements Shrimp water quality must be between 800-1000 mg SS/L.
Faxe supply, Faxe Wastewater Treatment Plant - Pre-dewatering and final dewateringTest type: Pre-dewatering laboratory test. Test type: First laboratory test for selection, then own performed full-scale test. The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. The plant has explanatory tanks and digesters. Both pre-drainage and final drainage are carried out at the plant. Surplus sludge is added to the treatment plant from two smaller biological treatment plants in the surrounding area. 1050 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for pre-drainage with requirements of 6-7% TS. Minimum TS% requirement for final drainage with requirements of 21-22% TS. Minimum requirements Shrimp water quality must be observed. Max 800 mg SS/L
Lolland Forsyning, Horslunde Wastewater Treatment PlantTest type: Laboratory test The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. Final drainage is carried out at the plant. No surplus sludge is brought to the treatment plant from other treatment plants. Minimum TS% requirement for final drainage with requirements of 18-20% TS. Minimum requirements Shrimp water quality must be observed. Max 400 mg SS/L
Lolland Forsyning, Søllested Wastewater Treatment PlantTest type: Laboratory test The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. Final drainage is carried out at the plant. Surplus sludge is added from 1 small biological treatment plant in the surrounding area. Sludge from this is drained together with sludge from Søllested Wastewater Treatment Plant.Minimum requirement of TS% for pre-drainage with requirements of 18-20% TS. Minimum requirements Shrimp water quality must be observed. Max 400 mg SS/L
Lolland Forsyning, Hunseby Wastewater Treatment PlantTest type: First laboratory test for selection, then own performed full-scale test. The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. 500 kg of polymer must be supplied for own full-scale test. Minimum TS% requirement for final drainage with requirements of 20 -23% TS. Minimum requirements Shrimp water quality must be observed. Max 400 mg SS/L
Lolland Forsyning, Rødbyhavn Wastewater Treatment PlantTest type: First laboratory test for selection, then own performed full-scale test. Final drainage is carried out on a shelter gget.er a mechanical, chemically, biologically active sludge plant. Surplus sludge is added from 1 small biological treatment plant and sludge from trix tanks. The run-in sludge is dewatered at the plant together with sludge from Rødbyhavn Wastewater Treatment Plant.270 kg of polymer will be supplied for our own full-scale test. Minimum TS% requirement for final drainage with requirements of 20-23% TS. Minimum requirements Shrimp water quality must be observed. Max 400 mg SS/L
Lolland Forsyning, Dannemare Wastewater Treatment PlantTest type: Laboratory test The wastewater treatment plant is a mechanical, chemically, biologically active sludge plant. Final drainage is carried out at the plant. Minimum TS% requirement for final drainage with requirements of 18-20% TS. Minimum requirements Shrimp water quality must be observed. Max 400 mg SS/L