A100, 16. BA - AD Neukölln to AS Am Treptower Park - Lot 81 Traffic Engineering
- approx. 8 pcs mast with horizontal extension.
- approx. 8 pcs. foundation
- approx. 4500 m Energiekabel
- approx. 70 hours of traffic data acquisition with transmission
- ca. 32 St. LWL-Switch
- approx. 40 hours commissioning and testing
- ca. 100 St. Radardetektor
- ca. 20 St. Wechselverkehrszeichen
- approx. 102 variable message signs overhead
- ca. 23 St. Wechselwegweisung
- approx. 6 pcs. guide barriers cpl. m. Foundation