It concerns the contracting of a framework agreement for the delivery of at least 1 600 and up to 2 000 kilometres of high voltage cables EV for Projects.
With regard to the size of the assignment, ProRail expects to purchase 200 km of cable annually, it will consist of:
— YmekrvasLqwd Fca 6/10 kV 3x240AI +as70 (90% of the business),
— YmekrvasLQWD Fca 18/30 kV 1x240Ai+AS25 (5% of business),
— YmekrvasLqwd Fca 12/20 kV 1x630al+AS35 (5% of business).
The maximum delivery time for cables mentioned above is six months.
ProRail also wants to be able to take the other cables described in the guide.
These types of cables are only used in specific situations. Therefore, they will not be forecast and if necessary be taken on request with then current prices and delivery times.
The term of the framework agreement is four years plus twice a two-year option.
At least 1,600 and a maximum of 2 000 kilometres.