Adaptation of the outdoor area of the extension building at the Degerfeldschule in 35510 Butzbach (gala construction work)
General construction description:
This bill of quantities describes the construction of the outdoor facilities of the extension of the Degerfeldschule in Butzbach. The construction phase includes the outdoor area of the building extension, the extension area of the playground, the route to the transformer and the construction of a swing system.
The construction project consists of the following work:
- paving work for the construction of paths and entrances,
- vegetation works,
Furthermore, drainage facilities, enclosures including gate systems and general installations are to be built as part of the construction of the outdoor facilities.
Trade description:
Execution in three sections
approx. 1.400 m3 Bodenbewegungen
approx. 1,070 m2 of path and square pavements
approx. 170 m Tiefbordsteine
approx. 105 m steel liner and paving lines
approx. 105 m Concrete Blockstufen
approx. 15 m concrete and limestone seating blocks
approx. 80 m wall angle up to 130 cm
approx. 7 pcs prefabricated masonry stringers
approx. 105 m drainage channels
ca. 105 m2 Sandspielfläche
approx. 50 m of robinia wood, edgings and palisades
approx. 125 m steel mesh fence with 4 gate systems
approx. 180 m trench excavation for electrical and drainage lines
approx. 520 m2 planting area incl. finishing care
approx. 1,700 m2 of lawns incl. finishing maintenance
approx. 17 pcs tall trunks incl. completion maintenance
1 piece of playground equipment Sand play area
1 piece of playground equipment double swing
1 pc garbage enclosure with canopy
as well as benches, waste bins, bicycle racks, handrails, tree slice, clean grids, signage and the renovation of the past. Toys
Due date:
Production of outdoor facilities: CW 47 (2023) - CW 28 (2024),
Planting: CW 25 (2024) - CW 42 (2024)