The city of Sulzbach intends to rehabilitate the “forest pool”.
The existing heat hall is partially demolished. Subareas of the basement are being rehabilitated and expanded. On the
A new heat hall and functional rooms will be built on the basement floor.
The existing pools (swimmers 'and non-swimmers' pools) will be renovated by installing stainless steel pools.
The pool surrounds and outdoor facilities in the area of the bathing area are being renewed.
The existing pool water treatment system will be completely renovated, and the external piping will be installed adapted to the new pool facilities.
Rohrgäben and KG pipes approx. 310 m
Holes and seal insert up to DN 300
PE 100 water pipes +3 outdoor showers approx. 340 m
district heating line 72 m
concrete block paving and base layers 1,450,000 m²
Asphalt 150 m²
block steps and concrete benches