Between Groß-Reken and Dülmen, the gap is to be closed by means of a continuous motorway. The planned road of the B67n / B474n between Isselburg-Werth and Dülmen will be rebuilt in the 1st construction phase already in a length of 4,500 m. Part of this tender is the embankment of construction phase 2.2 over a length of approx. 2,200 m. In construction phase 2.2, the embankment extends between the overpass structure No. 1 and the overpass structure No. 4.
The new construction project is located in the administrative district of Münster, Coesfeld and Borken. In detail, reference is made to the presentation in the execution plans.
The planned embankment in construction phase 2.2 starts east of structure 1 at construction km 0+200 and runs parallel to the L 600, leads over structures 2 and 3 and ends at construction km 2+280 west of structure 4.
The construction of the service road (axis 122) in unbound construction is also part of this tender.
The tendered services include the embankment filling for construction phase 2.2 between structures 1 and 4, the construction of the service road including access roads and bypass during construction, the construction of the ditch or trough as well as the construction of the culverts.
The work advertised in the specification of services includes the following main services:
approx. 22,200 m³ topsoil removal and storage
approx. 4,800 m³ of earthworks, demolition
approx. 49,000 m³ earthworks order
approx. 68,000 m³ earthworks order for backfill
approx. 14,300 m³ soil replacement
approx. 41,200 m² soil improvement
approx. 2,500 m of trench making
Laying approx. 14 m DN 300 pipelines
Laying approx. 53 m of DN 1,000 pipelines
approx. 3.300 m3 Frostschutzschicht 0/45
approx. 27.600 m³ Oberbodenauftrag
make approx. 1,250 m trough