The subject of the contract is the implementation of the task entitled Reconstruction of heating networks in traditional technology into a network in pre-insulated pipe technology in the area of Piłsudskiego - Dworcowa Street, i.e. execution of construction works consisting in the replacement of existing networks
thermal works made in the traditional system for the heat network in the technology of pre-insulated pipes in Olsztyn, from the Contractor's materials under the project entitled "Reduction of the emissivity of the economy by improving the efficiency of heat distribution in Olsztyn as a result of the reconstruction of the network and heating nodes – stage III".
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition works,
• earthworks,
• purchase, delivery and assembly of fittings, pipelines,
• land development and organization,
• construction of heating networks,
• required pickups.
b) Preparation of geodetic inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• felling trees and shrubs,
• implementation of the BIOZ plan,
• occupation of land, including road lanes and payment of related fees,
• notifying property managers about the planned date of work,
• preparation of the site for construction along with its marking,
• development of a traffic organization project,
• securing the construction site against access by third parties,
• providing geodetic services for investments,
• solving the issue of water and electricity consumption,
• installation of bottoms and network by-passes, provided for in the project documentation,
• restoration of the area and surface to the previous state, confirmed by a protocol signed by
the manager or owner of the site,
• insurance against civil liability to the extent specified in the draft contract,
• construction insurance against damage that may occur and against sudden, random events and
civil liability of works, construction equipment and equipment,
• removal of debris and other demolition materials, including waste disposal
The subject of the contract is the implementation of the task entitled Reconstruction of heating networks in traditional technology into a network in pre-insulated pipe technology in the area of Piłsudskiego - Dworcowa Street, i.e. execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heat network in pre-insulated pipe technology in Olsztyn, from the Contractor's materials under the project entitled "Reducing the emissions of the economy by improving the efficiency of heat distribution in Olsztyn as a result of reconstruction of the network and heating nodes – stage III".
A detailed description of the subject of the contract specifies:
Incl. No. 1- Construction project of Piłsudskiego Street - Dworcowa
Incl. No. 2- Bill of quantities Piłsudskiego Street - Dworcowa
Incl. No. 3 - Technical Specification for the Execution and Acceptance of Works.
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition work,
• earthworks,
• purchase, delivery and installation of fittings, pipelines,
• landscaping and ordering of the land,
• construction of thermal networks,
• Reception required.
b) Execution of surveying inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• felling trees and shrubs,
• implementation of the BIOZ plan,
• site occupation, including road lanes and payment of related charges,
• notification of property managers of the planned time limit for carrying out the work,
• preparation of the site for construction with its signage,
• development of a road traffic organization project,
• safeguarding the construction site against third party access,
• ensuring the operation of surveying investments,
• solving the question of water and electricity consumption,
• assembly of network by-streaks provided for in the design documentation,
• restoration of the site and pavement to the previous condition, confirmed by the protocol signed by the site manager or owner,
• insurance against civil liability to the extent specified in the draft contract,
• construction insurance against damage likely to occur and from sudden, random events and civil liability works, equipment and construction equipment,
• exportation of debris and other demolition materials, together with waste disposal.