New construction of a specialist nursing home - shell construction work
Excavation of the excavation pit and floor slab with dewatering measures, floor slab and outer walls of the basement in waterproof concrete, exterior walls on the ground floor and upper floor as double-shell solid construction, interior walls partly in masonry and exposed concrete, false ceilings as reinforced concrete elements
approx. 11,000 m² excavated earth, approx. 5,000 m² external masonry, approx. 350 m² floor slab, approx. 5,000 m² reinforced concrete walls, approx. 7,000 m² reinforced concrete ceilings, approx. 900 m² waterproofing, approx. 1,700 m² insulation