New construction of vocational school Weilheim - 2019 / 11.2 / 011 - 309 carpentry and steel construction I.
1. General
- Construction site equipment for services of the contractor, as well as general u. a,
- special construction site equipment and safety equipment,
- planning services AN,
- Documentation.
2 steel construction works
- execution class EXC2,
- steel components, HEA beams and round columns: 21 275 kg,
- constructive connections and connections;
- Cutouts and holes.
3 carpentry work
- Roof construction prefabricated elements made of shuttering, rafters, spruce purlins and glued laminated timber predominantly GL24h, partially GL28h, glazed surfaces:
- 2 basic types:
- different fitting elements
Total amount of wood of prefabricated roof construction:
- Formwork FSH: 310 m
- Rafter, directional purlin BSH GL24h: 625 m
- Filling wood BSH GL28h: 60 m
- Breakthroughs and recesses in prefabricated elements
- for TGA: 120 pieces,
- for skylights: 22 pcs.
- Acoustic measures on prefabricated elements made of wood wool panels with mineral wool support in 60 cm wide strips, with mounting timbers and empty piping for TGA:
- Direct mounting: 620 m
-. with wooden substructure: 1 980 m
v Empty pipe EN 20-20: 1,120 m.
- Individual components FSH and BSH
- Gurthölzer made of laminated veneer lumber: 1 100 m,
- Girders various formats of glulam GL24h: 75 m
- Glulam beams GL28h: 3 m
- Glulam beams GL36hyb: 52 m
- Constructive connections and connections
- various connections and connection points, among others,
- joints close swelling mortar: 1 180 m.
- skylight systems
- Plastic skylights: 6 pcs,
- Glazed skylights with solar control glazing: 7 pcs,
- skylight systems as shed glass construction predominantly light strips: 10 pcs.
- vapor barrier
- vapor barrier, Elastomerbitumenbahn mechan. attached: 6 900 m
- Vapor barrier, bitumen welding line V60S4 AL: 885 m
- Building physics connections
- various connections, etc.,
- joints close mineral wool: 1 135 m.
- Fire protection drywall works
- Aeration linings TGA breakthroughs: 100 pcs,
- Smoke shaft prefabricated part: 1 pc.