The tendered service includes the following:
1. Heating/cooling ceiling and accessories
2. Special services
3. Stundenlohnarbeiten
4. Revisionsunterlagen
The new building Building D will be built between buildings C and E. The building has 5 storey levels from the site as well as an attached roof centre.
On the north-west side, the building cantilevers with operating theatre and technical floors on the 1st and 2nd floors. (Drawer)
The new structure connects to the crossbar of component C2 in all levels.
The new building D is accessed on the same level via the C-connection building. The existing elevator C-connection
will be renovated and will be expanded to two elevators.
The D-building has a necessary staircase in each case.
The façade of the new building will be continued in the design of the existing building.
The cantilevered structure is equipped with a façade made of compact panels with vertical aluminium slats as sun and privacy protection.
The levels of the new building D (E-1 to E 4 and technical superstructures E5) each form fire subsections / smoke compartments.
In some areas, usage units will be realized.
Smoke extraction from the corridors is carried out via corridor windows or windows.
adjacent area or a SHEV in the ceiling cavity.