Together with the municipality of Upahl, the city of Grevesmühlen intends to develop an intermunicipal large-scale commercial site north of the A20 federal motorway.
The prerequisite for commercial settlement is, among other things, the provision of drinking water and ensuring wastewater discharge by the Grevesmühlen special purpose association.
The subject of the award procedure are the planning services for drinking water and wastewater for the object planning of civil engineering structures in accordance with Part 3, Section 3 HOAI 2021 and for the specialist planning of technical equipment in accordance with Part 4, Section 2 HOAI 2021 for the external development of the intermunicipal large-scale business location Grevesmühlen/Upahl.
Together with the municipality of Upahl, the city of Grevesmühlen intends to develop an intermunicipal large-scale commercial site north of the A20 federal motorway.
The prerequisite for commercial settlement is, among other things, the provision of drinking water and ensuring wastewater discharge by the Grevesmühlen special purpose association.
The subject of the award procedure are the planning services for drinking water and wastewater for the object planning of civil engineering structures in accordance with Part 3, Section 3 HOAI 2021 and for the specialist planning of technical equipment in accordance with Part 4, Section 2 HOAI 2021 for the external development of the intermunicipal large-scale business location Grevesmühlen/Upahl.
The respective service phases for the plant components to be planned are 1st building:
1.1 HOAI 2021 § 43 Performance profile Civil engineering structures, service phases 3-9 1.2 HOAI 2021 Appendix 12.1 Local construction supervision 1.3 Compilation of the overall documentation (inventory documentation) 1.4 Coordination and lead during commissioning 1.5 Factual report and cost compilation for subsidies 2. Technical plants – HOAI 2021 § 53 Plant groups 1, 3, 6, 7 (machine technology):
2.1 HOAI 2021 § 55 Performance description Technical equipment, work phases 3-9 2.2 Preparation for the complete documentation (inventory documentation) 2.3 Preparation during commissioning.
2.4 Factual report and cost summary for subsidies The service is to be commissioned in stages as follows.
Level 1: LPH 1-4 Level 2: LPH 5-9 plus the special services required in each level.
The following drinking water pipes must be planned to ensure that drinking water supply meets requirements:
New installation 3.900 m TW-line DN 250 WW Wotenitz > IGG Grevesmühlen/Upahl Neuverlegung 1,500 m TW-line DN 250 IGG Grevesmühlen/Upahl -> pressure station Upahl (for new installation 2,560 m TW-line DN 200 WW Wotenitz -> Questin).
The following waste water pressure pipes must be planned for wastewater discharge in line with requirements:
New installation 7,200 m AWD line DN 250 IGG Grevesmühlen/Upahl -> KA Grevesmühlen Relaying 2,600 m AWD line DN 250 GG Upahl -> IGG Grevesmühlen/Upahl.
Among other things, the necessary crossings of a railway line and second-order water crossings must be taken into account.