Road construction works | Tenderlake

Road construction works

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
07 August 2023
Closing Date:
13 September 2023
Location(s):
DEA13 Essen, Kreisfreie Stadt (DE Germany/DEUTSCHLAND)
Description:
Road and track construction work on Hollestraße in Essen, Citybahn project, VE 3.1

Road and track construction work on Hollestraße in Essen, Citybahn project, VE 3.1

The allocation unit 3.1 is the 1st construction phase of the station pole harvest and extends between

the street Am Hauptbahnhof and the Steeler Straße on a new construction length of about 600 m.

In connection with the construction of the new track, the road cross-section is redesigned

as well as the barrier-free new construction of the Hauptbahnhof and Hollestraße Süd stops.

The project is being put out to tender by the joint venture between Ruhrbahn GmbH (RB) and the City of Essen, Office for Roads and Transport (ASV).

Today, the city of Essen has a tram network of more than 50 km long, which extends over approx. 5 km

in tunnel position and over a good 5 km on a special track body. The tunnel around the

The Central Station / Town Hall / Berliner Platz area is already reaching its capacity limits. Before

The background of high line capacity utilisation and predicted passenger growth is to be countered by the

Construction of the station pole harvest as a bypass to relieve the tunnel system.

The station pole harvest is part of a planned, approx. 5.4 km long above-ground extension or new construction

route, which, in addition to eliminating the capacity bottleneck in the tunnel, also provides access to the

Development area Essen 51 is to serve.

The overall "Citybahn" project consists of the three planning phases, which will be used as station stations.

gente (BHT), Berthold-Beitz-Boulevard 3rd construction phase (BBB-3.BA) and Essen 51

the. The Bahnhofstangente section runs from the new Schwanenkampbrücke stop in

the Hachestraße in the west to the new stop Betriebshof Stadtmitte in the Goldschmidt-

road in the north-east.

The tender unit 3.1 Road and track construction work Hollestraße is the 1st construction phase of the railway

Hofstangente and extends between the street Am Hauptbahnhof and the Steeler Straße on

a new construction length of about 600 m. In connection with the construction of the new track, the redesign of the

the construction of the cross-section of the road as well as the barrier-free new construction of the main station and

Hollestraße Süd.

The entire tender for the award unit VE 3.1 Straßen- und Gleisbau Hollestraße is divided into

are divided into the superordinate parts of tram operating facilities and road transport facilities, where:

the tram operating facilities consist of only Part 01. The road transport facilities are

on the other hand, several parts, part 02 to part 06.

Tram operating facilities (commissioned by Ruhrbahn GmbH):

Part 01:

Title 01.01 General services

Title 01.02 Works for proof

Title 01.03 Dismantling/demolition/earthworks

Title 01.04 Drainage works

Title 01.05 Cable civil engineering, AZK, cabinets

Title 01.06 Foundations catenary / stop equipment

Title 01.07 Track construction work

Title 01.08 Road works

Title 01.09 Platforms / Entrances

Title 01.10 Landscaping

Title 01.11 Maintenance work on grass tracks (1st and 2nd year)

Road traffic facilities (commissioned by the ASV):

Part 02:

Title 02.02 Earthworks

Title 02.03 Drainage works

Title 02.04 Base courses according to ZTV T-StB and ZTV SOB-StB

Title 02.05 Asphalt works

Title 02.06 Edge fastenings

Title 02.07 Paving slabs and slab coverings according to ZTV Pflaster-StB

Title 02.08 Construction site equipment

Title 02.09 Construction site and traffic safety

Title 02.10 remains blank

Title 02.11 Special Items

Title 02.12 Brücke Gildehofstraße

Title 02.13 Bridge Bernestraße

Part 03: Lighting

Part 04: Traffic lights

Part 05: Marking work

Part 06: Signage

The following services are carried out and delivered in Part 01 -

Straßenbahnbetriebsanlagen:

Absorb approx. 160 m³ of topsoil

Installing approx. 370 m³ of topsoil

Absorb approx. 5,360 m³ of soil

Absorb approx. 900 m² of paving and slabs

approx. 1,935 m of curbs and gutters

approx. 4150 m² of bound road superstructure

approx. 840 m³ soil replacement

approx. 630 m Entwässerungsleitungen DN 150 – DN 200

(connecting pipes and drainage pipes as partial seepage pipe))

ca. 440 m Rasengleis TRAVETTO INPLACE-B (49E1 / 60R2)

with 2,700 m² of lawn cover

approx. 665 m of track on mounting blocks - type B -

with 2,400 m² of asphalt cover

1 pc track change with simple switches on concrete swelling

approx. 730 m Betonbordsteine

approx. 510 m Gussasphaltrinne

approx. 405 m² semi-rigid surface course

approx. 210 m line marking (solid and broken lines)

approx. 16 directional arrows / pictograms

approx. 110 m² Sperrflächen

approx. 660 m² stop Hauptbahnhof as central platform (Strab / Strab)

approx. 490 m² stop Hollestraße Steig 4 as a combined platform (Strab / Bus)

approx. 3,300 m cable conduit DN 50, DN 63 and DN 110 in the cable trench

approx. 25 cable ducts

approx. 10 foundations for stop equipment and stop roof

approx. 20 boreholes for catenary pylons

The track material in the form of switches and rails with fastening and insulation is provided by

the AG.

Within the framework of Part 02 Road construction, the following items are carried out:

Approx. 6,480 m³ of bound road superstructure

Approx. 4,420 m² of paving and slabs

approx. 2,605 m of curbs and gutters

Absorb approx. 260 m³ of topsoil

approx. 5,155 m³ of unbound road superstructure

approx. 1,300 m³ of soil H2

ca. 7.500 m² Asphalttragschicht AC 22 T S

approx. 7.500 m² Asphaltbinderschicht AC 16 B S

ca. 6.900 m² Asphaltdeckschicht SMA 8 S

approx. 110 m² semi-rigid ceiling

Produce approx. 5,100 m² of paving and slabs

Create approx. 1,300 m² of green space

approx. 2.160 m Gussasphaltrinne

approx. 3.300 m Betonbordsteine

approx. 57 road drains

approx. 870 m drainage pipes DN 150 to DA315 (plastic)

For execution and delivery, the following are included in Part 03 Lighting:

approx. 7,700 m cable conduit DN 53, DN 93 and DN 110 in the cable trench

approx. 19 cable ducts

approx. 59 pylon foundations with lighting pole and luminaires,

complete cabling

In Part 04 Traffic light systems, the following are included in the design and delivery:

approx. 4,600 m cable conduit DN 53, DN 93 and DN 110 in the cable trench

approx. 41 cable ducts

approx. 31 pylon foundations with LSA mast and luminaire

In addition to the execution and delivery, the following marking work is carried out in Part 05:

approx. 1,700 m line marking (solid and broken lines)

approx. 36 pieces of directional arrows / pictograms

For execution and delivery, the following are included in Part 06 Signage:

Produce approx. 64 pieces of traffic signs with poles

Download full details as .pdf
The Buyer:
Ruhrbahn GmbH
CPV Code(s):
34928470 - Signage
34993000 - Road lights
45233120 - Road construction works
45233221 - Road-surface painting work
45234116 - Track construction works
45316212 - Installation of traffic lights