The municipality of Weßling intends to build a new primary school building for all of its 3 districts using wood.
The main building comprises a slope floor / basement, the ground floor and an upper floor (= top floor).
The following services are mainly awarded with this ticket: Screed work.
Waterproofing work on reinforced concrete base plate 600m2.
Screed work:
Total (screed/heated screed): 3.425m2
Cement screed, floating, single-layer heating screed total: approx. 2,600m2 total
(1,850m2 for parquet flooring, 265m2 for epoxy resin coating, 230m2 for tile covering, 35m2 for clean-up zone)
Cement screed, laid floating, two-layer heating screed as a visible screed with surface sealing 825m2.
Coating work:
Coating work on STB base plate, smoothed wings, with dust-binding paint 185m2
Coating work on cement screed surfaces with epoxy resin paint 265m2.