The subject of the contract is the implementation of the task entitled Reconstruction of heat networks in traditional technology into a network in the technology of pre-insulated pipes: Task 1 – in the area of Warmińska – Mazurska Street, Task 2 – in the area of Piłsudskiego Street, Dworcowa, i.e. execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heat network in the technology of pre-insulated pipes in Olsztyn, from the Contractor's materials as part of the project entitled "Emission reduction economy by improving the efficiency of heat distribution in Olsztyn as a result of the reconstruction of the heating network and nodes – stage III".
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition work,
• earthworks,
• purchase, delivery and installation of fittings, pipelines,
• landscaping and ordering of the land,
• construction of thermal networks,
• Reception required.
b) Execution of surveying inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• felling of trees and shrubs,
• implementation of the BIOZ plan,
• site occupation, including road lanes and payment of related charges,
• notification of property managers of the planned time limit for carrying out the work,
• preparation of the site for construction with its signage,
• development of a road traffic organization project,
• safeguarding the construction site against third party access,
• ensuring the operation of surveying investments,
• solving the question of water and electricity consumption,
• installation of network bottoms and by-passes, provided for in the project documentation,
• restoration of the site and pavement to the previous condition, confirmed by the protocol signed by the site manager or owner,
• liability insurance to the extent specified in the draft contract (which is Annex 5 to the SWZ),
• construction insurance against damage likely to occur and from sudden, random events and civil liability works, equipment and construction equipment,
• exportation of debris and other demolition materials, together with waste disposal.
Task 1 – in the area of Warmińska – Mazurska StreetThe subject of the contract is the implementation of the task entitled Reconstruction of heat networks in traditional technology into a network in the technology of pre-insulated pipes: Task 1 – in the area of Warmińska – Mazurska Street, i.e. execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heating network in the technology of pre-insulated pipes in Olsztyn, from the Contractor's materials as part of the project entitled "Reducing the emissivity of the economy by improving the efficiency of distribution heat in Olsztyn as a result of reconstruction of the heating network and nodes – stage III".
A detailed description of the subject of the contract specifies:
Appendix No. 1.1 – Land development project ul. Warmia – Masuria
Attachment No. 1.2 – Technical design of ul. Warmia – Masuria
Attachment No. 1.3 – Bill of quantities ul. Warmia – Masuria
Annex No 4 — Technical Specification for the Performance and Reception of Works.
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition work,
• earthworks,
• purchase, delivery and installation of fittings, pipelines,
• landscaping and ordering of the land,
• construction of thermal networks,
• Reception required.
b) Execution of surveying inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• felling of trees and shrubs,
• implementation of the BIOZ plan,
• site occupation, including road lanes and payment of related charges,
• notification of property managers of the planned time limit for carrying out the work,
• preparation of the site for construction with its signage,
• development of a road traffic organization project,
• safeguarding the construction site against third party access,
• ensuring the operation of surveying investments,
• solving the question of water and electricity consumption,
• installation of network bottoms and by-passes, provided for in the project documentation,
• restoration of the site and pavement to the previous condition, confirmed by the protocol signed by the site manager or owner,
• liability insurance to the extent specified in the draft contract (which is Annex 5 to the SWZ),
• construction insurance against damage likely to occur and from sudden, random events and civil liability works, equipment and construction equipment,
• exportation of debris and other demolition materials, together with waste disposal.
Task 2 – in the area of Piłsudskiego Street, DworcowaThe subject of the contract is the implementation of the task entitled Reconstruction of heat networks in traditional technology into a network in the technology of pre-insulated pipes: Task 2 – in the area of Piłsudskiego Street, Dworcowa, i.e. execution of construction works consisting in the replacement of existing heat networks made in the traditional system with a heating network in the technology of pre-insulated pipes in Olsztyn, from the Contractor's materials as part of the project entitled "Reducing the emissivity of the economy by improving efficiency heat distribution in Olsztyn as a result of reconstruction of the heating network and nodes – stage III".
A detailed description of the subject of the contract specifies:
Attachment No. 2.1 – Construction project ul. Piłsudskiego - Dworcowa
Appendix No. 3 – Measure żołnierska-Dworcowa Street
Annex No 4 — Technical Specification for the Performance and Reception of Works.
The scope of the order:
a) Construction and assembly works:
• dismantling and demolition work,
• earthworks,
• purchase, delivery and installation of fittings, pipelines,
• landscaping and ordering of the land,
• construction of thermal networks,
• Reception required.
b) Execution of surveying inventory and as-built documentation.
In addition, the Contractor is obliged on its own and at its own expense
in particular, to:
• felling of trees and shrubs,
• implementation of the BIOZ plan,
• site occupation, including road lanes and payment of related charges,
• notification of property managers of the planned time limit for carrying out the work,
• preparation of the site for construction with its signage,
• development of a road traffic organization project,
• safeguarding the construction site against third party access,
• ensuring the operation of surveying investments,
• solving the question of water and electricity consumption,
• installation of network bottoms and by-passes, provided for in the project documentation,
• restoration of the site and pavement to the previous condition, confirmed by the protocol signed by the site manager or owner,
• liability insurance to the extent specified in the draft contract (which is Annex 5 to the SWZ),
• construction insurance against damage likely to occur and from sudden, random events and civil liability works, equipment and construction equipment,
• exportation of debris and other demolition materials, together with waste disposal.