This public contract concerns a one-off contract for the construction of a new catering complex in Peutie. This file consists of 3 phases:
1. The installation of a temporary kitchen;
2. The demolition of the old horeca complex followed by the construction of the new horeca complex;
3. The dismantling of the temporary kitchen.
A partial provisional approval will have to take place at the end of phases 1 and 2. A suspension of the execution time will also take place at the end of phases 1 and 2 to allow the relocation of the facilities to, respectively, the temporary kitchen and the new horeca complex. The relocation of the facilities is the responsibility of the Defence.
This public contract concerns a one-off contract for the construction of a new catering complex in Peutie. This file consists of 3 phases:
1. The installation of a temporary kitchen;
2. The demolition of the old horeca complex followed by the construction of the new horeca complex;
3. The dismantling of the temporary kitchen.
A partial provisional approval will have to take place at the end of phases 1 and 2. A suspension of the execution time will also take place at the end of phases 1 and 2 to allow the relocation of the facilities to, respectively, the temporary kitchen and the new horeca complex. The relocation of the facilities is the responsibility of the Defence.