The tendered construction work includes the following objects:
- Excavation, securing and cladding of access tunnels:
Length approx. 670 m, excavation cross-section approx. 24 m2
- Excavation, securing and cladding as well as interior fittings of the power plant headquarters:
Ausbruchkubatur ca. 3'000 m3
- Excavation, securing and cladding pressure tunnels Ärlen – Handeckfluh:
Length approx. 990 m, excavation cross-section approx. 14 m2
- Excavation, securing and cladding underwater tunnels:
Length approx. 110 m, excavation cross-section approx. 8 m2
- Rear concreting of steel armor
The tendered construction work includes the following objects:
- Excavation, securing and cladding of access tunnels:
Length approx. 670 m, excavation cross-section approx. 24 m2
- Excavation, securing and cladding as well as interior fittings of the power plant headquarters:
Ausbruchkubatur ca. 3'000 m3
- Excavation, securing and cladding pressure tunnels Ärlen – Handeckfluh:
Length approx. 990 m, excavation cross-section approx. 14 m2
- Excavation, securing and cladding underwater tunnels:
Length approx. 110 m, excavation cross-section approx. 8 m2
- Rear concreting of steel armor