The subject of the present invitation to tender for the renewal of the Robbia power station is all construction work for the construction of the Puntalta - Robbia section III pressure line, including the cable pipe block and in-situ concrete shafts.
Main amounts:
- Delivery and installation of pressure line DN 1300 650 m,
- Excavation / backfilling 200 fm
- concrete 910 m
- reinforcement 76 t,
- micropiles 80 m,
- Cable pipe block 650 m.
The subject of the present invitation to tender for the renewal of the Robbia power station is all construction work for the construction of the Puntalta - Robbia section III pressure line, including the cable pipe block and in-situ concrete shafts.
Main amounts:
- Delivery and installation of pressure line DN 1300 650 m,
- Excavation / backfilling 200 fm
- concrete 910 m
- reinforcement 76 t,
- micropiles 80 m,
- Cable pipe block 650 m.