The city of Göttingen intends to renovate the existing, listed outdoor pool on Brauweg and make it more attractive.
All pools are to be fundamentally revised.
This includes the dismantling of all outdoor paving surfaces, the removal of all overflow channels, the removal of the film lining, demolition of the pool heads. The bathing water technology must be largely renewed and partially revised. All basins receive new stainless steel gutters and a new foil lining. The non-swimmer pool West will be converted into a children's pool. The walk-through basins will be demolished and replaced by barrier-free walk-through troughs. The entire bathing water technology is renewed and a new rainwater drainage pipe is laid. The existing large slide, as well as the historic diving tower are to be preserved and protected during the construction project. The existing children's pool will be partially demolished and converted into a dry playground. After completion of the pools, the paving areas will be provided with new coverings and the transitions to the higher sunbathing lawn will be revised in landscape planning. The shore areas of the leine are opened on both sides and integrated into the bathing operation as a nature experience space. The two Leineufer connected with a new play suspension bridge. At the same time, the entrance building is being renovated in accordance with monument regulations. The processes of the two separate construction projects must be coordinated with each other in such a way that no hindrances arise.
Total area of outdoor swimming pool: 17,574 m²
Water surfaces: 2,367.04 m²
Plantings and hedges: 370 m²
Trockenspielplatz: 200 m²
Lawns/lawns: 10,600 m²
Right-sided Leinewiese: 3.600m²
Paved areas: 3.650m²
The construction site access is to be approached from the north via the Brauweg, the middle access road and the roundabout. Parking is available in front of the west wing of the entrance building. To be created The construction site will be reached in an easterly direction via the existing cycle path, where a separation with a construction fence takes place. A secured entrance gate with access scrolls borders the construction site. A construction road and a paved turning circle must be built around the construction site that can be used in oncoming traffic. There is limited storage space on the premises. These can be found in the construction site equipment plan. There are 4 sanitary containers and 3 office containers. A guard container and barrier to secure the site are available. A lockable storage container provided by the client can be used on the premises.
The property south of the Leine is reached from the sand path and is only available for the work on the construction of the play bridge. The existing bridge is not passable.
The in-situ concrete children's paddling area will be built within the existing pool body of the former non-swimmer pool. The pool bodies, overflow channels and stairs are lined over the entire surface with differently coloured, sanded GRP local laminate. Gutter grates must be supplied and installed.
The following water attractions are planned:
2 themed water cannons
3 thematically designed spray figures (knight damsel and dragon)
Wasserdüsen in Ortbetonwand
5 Standduschen in Durchschreitemulden
1 new children's slide for the non-swimmer pool east.
Revision of an existing water fungus.
-Tent for the construction period
-Coating of all pools 240 sqm
-Spray figures 3 pieces
-Water cannons 2 pieces
-Nozzles in Vertical Wall 3 pieces
-Rinnenroste 52 lfdm
-Remediation of water fungus
-Outdoor stand showers 5 pieces
-Children's slide open on steel construction incl. Staircase
-incl. starting platform with polymer concrete steps