Sports ground
— component A, B, C school,
- Component D new sports hall.
Cross-component measures
Construction site equipment over the performance period sports floor
Create a pitch map school components A, B, C
— approx. 53 m
— approx. 31.8 m hardwood skirting board 60/20 mm standing, surface RAL 9002,
— 1.0 m of double-chamber profile, transition ancillary rooms,
Sports hall component D.
— ca. 819 m
— approx. 819 m
— approx. 819 m
— approx. 819 m
— clean approx. 103 m
— approx. 103 m
— approx. 103 m
— approx. 63 m remove edge strips, equipment rooms,
— approx. 103 m
— 15 tool sleeve covers round/square 50 to 100 mm
— 10 locking plates for sports equipment,
— approx. 63 m hardwood skirting board 60/20 mm standing, surface RAL 9002,
— approx. 6.55 m transition profiles, stainless steel,
— approx. 8.85 m double chamber profile, crossing ancillary rooms 1742,
— record 70 m of playing field markers with 2K PUR color approximately 922,
— 6 m
— approx. 400.0 m
— 405.0 pcs hall protective lining, floor protection mats,
— 2.0 pcs transport trolleys, floor protection mats.