Construction of a combined heat and power plant at the site of the Leonberg biowaste fermentation plant
Betriebsbereiche:
-Power plant:
consisting of the main components:
· CHP, 560 kWth and 530 kW el
· Buffer tank 35 m3
· Reserve peak load boiler 850 kW with burner heating oil/ biogas
· Druckhaltung/ Nachspeisung
· Fernwärmepumpen
· Double walled heating oil tank
· Pipeline construction within the delivery limits
· Desulphurisation plant for biogas
- Signalaustausch:
The signal exchange for the transmission of operating and fault messages with the following on-site lots shall be produced by the Contractor:
- The Vergärungstechnik
- Batch superordinate control technology
- Lot fire alarm system (emergency shutdown)