In the Frutigen substation, SBB intends to procure a 33.33MVA, 16.7Hz overhead line transformer. Delivery of the transformer is planned for May 2021.
The delivery includes manufacturing, FAT, transport, unloading, assembly and testing on site of the new 33.33 MVA transformer 132.8 / 17.1kV. The disposal of the existing transformer is not included in the scope of delivery.
We will carry out a plant inspection at the Frutigen substation on January 9, 2019 at 10:00 a.m.
Meeting point: entrance to Frutigen substation
Altenweg 31, 3714 Frutigen
The participants must take a helmet (not white), a light vest and sure-footed shoes with them and wear them during the inspection.
The number of participants per provider is limited to 2 people. The registration, with the names of the participating persons and company, must be sent to the following e-mail: purchasing.energy@sbb.ch by 7.1.2020 12:00.
In the Frutigen substation, SBB intends to procure a 33.33 MVA, 16.7 Hz contact line transformer. The transformer is scheduled for delivery in May 2021.
The delivery includes manufacturing, FAT, transport, unloading, assembly and testing on site of the new 33.33 MVA transformer 132.8 / 17.1kV. The disposal of the existing transformer is not included in the scope of delivery.
We will carry out a plant inspection at the Frutigen substation on January 9, 2019 at 10:00 a.m.
Meeting point: entrance to Frutigen substation
Altenweg 31, 3714 Frutigen
The participants must take a helmet (not white), a light vest and sure-footed shoes with them and wear them during the inspection.
The number of participants per provider is limited to 2 people. The registration, with the names of the participating persons and company, must be sent to the following e-mail: purchasing.energy@sbb.ch by 7.1.2020 12:00.