In the case of the construction project at the school building of the comprehensive school (46) Friedrich-Wilhelm-von-Steuben in Potsdam, the fire protection renovation and a far-reaching energy-efficient renovation are planned in several construction phases.
The work is carried out under the special conditions during ongoing school operations.
The services advertised here include tile work, including screed work.
The school building has two floors and a partial basement (limited for the house connections).
After the contract has been awarded, the service is to be provided in 5 construction phases:
- approx. 300 m² cement screed, floating in a complete layer structure, multi-part
- approx. 50 m² with slope
- approx. 300 m² floor tiles with preparation of substrate and waterproofing
- approx. 400 m² of wall tiles with preparation of substrate and waterproofing
- Sanitary areas with safety mirrors
No