As part of the procurement, three lots, servers, SAN extensions and network components are put out to tender. The delivery is subject to tight time constraints, which is why a delivery must take place at the latest 8-10 weeks after the award of the contract. Due to the existing infrastructure, only Fujitsu products are requested for specific products. The delivery of other products is out of the question, otherwise there will be compatibility problems. Further details can be found in the tender documents.
Acquisition of serversThe subject of the tender is the acquisition of a new software-based storage solution and the increase in capacity through new servers and networks for the Baden-Württemberg State Criminal Police Office.
The order for lot 1 includes the delivery of devices, software and the services described below:
- 4x virtualization server; FUJITSU PRIMERGY RX2540 M5, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 2x virtualization server with GPU; FUJITSU PRIMERGY RX2540 M5, 2x20 GRID vPC NVIDIA licenses and 5 years of SUMS (support, maintenance, updates and subscriptions), including Fujitsu Support Pack Hardware 5 years of Onsite Service 9x5 NBD HDD retention;
- 10x firewall 1G; FUJITSU PRIMERGY RX2530 M5, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 8x 10G firewall; FUJITSU PRIMERGY RX2530 M5, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 2x server; FUJITSU PRIMERGY RX2540 M5, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 4x cold stand-by hard drives; 2x 1TB (compatible with firewall 1G and 10G); 2x 2.4TB SAS 10K (compatible with server).
The details of the order can be found in the specification (lot 1).
Important note: The complete delivery must be made within 8-10 weeks after the award of the contract.
Acquisition of SAN expansionThe subject of the tender is the acquisition of a new software-based storage solution and the increase in capacity through new servers and networks for the Baden-Württemberg State Criminal Police Office.
The order for lot 2 includes the delivery of devices, software and the services described below:
- 1x SSD storage for existing device; Eternus DX600 S3, SN: 4621535003, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 1x license extension (HA) for existing device; Eternus DX600, SN: 4621535003, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD Retention;
- 1x SAN for 2nd location; Eternus DX600, S5 with 2 controllers and license for software ETSF16 Feature Pack (Cluster Pack) DX600, including Fujitsu Support Pack Hardware 5 years Onsite Service 9x5 NBD HDD retention;
- 4x cold stand-by hard drives; 2x Value SSD 7.68TB for DX600S3; 2x Value SSD 7.68TB for SAN (2nd location);
- 1x hardware server + software (HA) Fujitsu Storage Cluster Controller for witnesses in the cluster; FUJITSU PRIMERGY RX1330 M4 Rack Server, including Fujitsu Support Pack Hardware 5 years onsite service 9x5 NBD HDD retention;
- 1x furnishing service; Commissioning 2. SAN setup ClusterPack / high availability.
Migrate the existing device LUNs to the cluster without disrupting operations.
The details of the order can be found in the specification (lot 2).
Important note: The complete delivery must be made within 8-10 weeks after the award of the contract.
Acquisition of network componentsThe subject of the tender is the acquisition of a new software-based storage solution and the increase in capacity through new servers and networks for the Baden-Württemberg State Criminal Police Office.
The order for lot 3 includes the delivery of:
- 4x 1G Top of Rack (ToR) switch; DGS-3630-28PC;
- 5x 1G switch without fan; DGS-1210-28;
- 4x power supply for ToR switch; DPS-700;
- 56x SFP + transceiver 10GbE-SR; DXS-3600-32S, DGS-3630-28PC;
- 4x SFP + DAC; DGS-3630-28PC;
- 2x LTE router; Connections LTE, WiFi, 3x LAN, 1x WAN, DualSIM;
- 2x SMS gateway;
- 2x DIN Rail Rackmount Kit;
- 5x sensors; HWg Poseidon2 3266.
The details of the order can be found in the specification (lot 3).
Important note: The complete delivery must be made within 8-10 weeks after the award of the contract.