Roof snow work in Kuopio area

Sansia will put out to tender the roof snow work in the City of Kuopio area on behalf of its partner Servica Oy.

A framework agreement is established in the procurement. The procurement is divided into twenty (20) areas. Tenders can be submitted for one or more areas. Three contract suppliers are being sought for each area in order of priority.

1. Kuopiohalli

2. Theatre House

3. Musiikkikeskus

4. City Hall

5. Taidelukio River

6. Nilsia Service Centre

7. Maaninka Sports and Youth Centre

8. Maaninka office building

9. Juankoski Health Centre

10. Länsi-Puijo School

11. Maaninkajärvi School

12. School of the Circular, Lower Circularity

13. Pitkälahti School

14. Kuikkalampi daycare centre

15. Valtuustotalo

16. Neulamäki School

17. Main Library

18. Juankoski Ironworks School, Middle School and Upper Secondary School

19. Game Water Service Centre

20. Other items

Roof snow works include the removal of snow and eaves icicles from the roof and the lifting equipment needed for snow removal.

If necessary, the client can also order roof snow work on the site on an hourly basis, for example, in the case of snow work on only part of the roof.

Work is ordered as needed, depending on e.g. winter snow situation or the customer's own resources. The client Servica Oy also carries out roof snow work itself and reserves the right to take care of the sites mentioned in this procurement in some winters also as its own work.

The procurement is described in more detail in the section "Description of the procurement" in the invitation to tender. Site-specific information is available via the link in the invitation to tender.

The framework agreement is planned to commence on 1.11.2023 and last until 31.10.2025. After this, there is an option period of two (2) years.

The subscriber does not commit to any order amounts.

Kuopiohalli

Kuopiohalli, Opistotie 4, 70200 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Länsi-Puijo School

Länsi-Puijo School, Pursutie 10, 70280 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Maaninkajärvi School

Maaninkajärvi School, Maaningantie 49, 71750 Maaninka

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Pyörön koulu, Alapyörö

Pyörön koulu, Alapyörö, Kulmakatu 7, 70820 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Pitkälahti School

Pitkälahti school, PItkälahdentie 4, 70800 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Kuikkalampi daycare centre

Kuikkalampi daycare centre, Kuivannonlahdenkatu 27, 70840 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Valtuustotalo

Council House, Suokatu 42, 70111 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Neulamäki School

Neulamäki School, Pinokuja 6, 70150 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Main library

Main Library, Maaherrankatu 12, 70100 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Juankoski Ironworks School, middle school and upper secondary school

Juankoski Ironworks School, Juankoskentie 34, 73500 Juankoski

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Riistavesi Service Centre

Riistavesi Service Centre, Museotie 3, 71160 Riistavesi

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Theatre House

Theatre House, Niiralankatu 2, 70600 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Other destinations

Other destinations

The client may also need to order roof snow work for occasional sites in their operating area. Work is ordered as needed, and the client defines the tasks to be ordered on a case-by-case basis.

The work to be commissioned may include, for example:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Musiikkikeskus

Music Centre, Kuopionlahdenkatu 23, 70100 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

City hall

City Hall, Tulliportinkatu 31, 70100 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Taidelukio River

Taidelukio River, Koljonniemenkatu 48 -50, 70100 Kuopio

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Nilsia Service Centre

Nilsia Service Centre, Pisantie 10, 73300 Nilsia

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Maaninka Sports and Youth Centre

Maaninka Sports and Youth Centre, Maaningantie 49, 71750 Maaninka

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Maaninka office building

Maaninka office building, Maaningantie 32, 71750 Maaninka

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.

Juankoski Health Centre

Juankoski Health Centre, Terveystie 9, FI-73500 Juankoski

The procurement includes roof snow work for the site:

- informing the users of the site about the roof snow work to be carried out in accordance with the Client's instructions

- construction of snow fall protection areas in accordance with site-specific requirements and guarding the area during snow removal work.

- snow removal and removal of eaves icicles in compliance with occupational safety legislation.

- the instructions for the work come from the Client. The snow drop sites are inspected/agreed on property-specific together with the client, before the work begins. Snow fall must not cause harm/danger to the structures/users of the property.

- dumping fallen snow in a designated place.

- ordering snow removal from the Customer's partner within the agreed schedule. (Snow removal is not part of the agreement)

- reporting of work to the Client: schedule for the start of work and performance of work

General requirements:

- The Client requires that the work is carried out safely in accordance with the Client's snow roof work instructions.

- in the event of snow fall, it is not possible to use machines that cause additional loads on roof structures, such as: snowblowers on the roof.

- Roof coatings or working methods/equipment damaging equipment/structures must not be used (e.g. iron rod, etc.)

- the Supplier is obliged to notify the Contracting entity immediately of any defects or deficiencies detected in connection with the work.

- Damage to roofing material caused by snow removal must be reported to the Customer immediately. The Client and the Supplier agree on repairing the damage on a case-by-case basis, the Supplier is responsible for the repair costs.

- acute defects that pose an immediate danger to users or structures must be repaired without delay and further damage must be prevented immediately

Hourly rate-based work:

The client may also need to order roof snow work on an hourly basis in the case of, for example, snow clearance. only partial snow fall on the roof. This is agreed separately with the supplier and the hourly rates given in the quote are used in the charge.