Overall dimensions: New construction (new construction component I) and restructuring (new construction / demolition component II and component III) of the previous comprehensive school Senefelder School Treuchtlingen in several construction phases with ongoing school operations.
As part of the restructuring, the three school types of middle school, junior high school and high school will be combined in one building under the roof of the integrated and differentiated comprehensive school and equipped with flexible rooms and learning areas.
Because the dimensions. Several construction phases are planned to take place during ongoing school operations:
- Preliminary run: partial cancel Existing building "Mensa" for new building measure BT I;
- 1st construction phase: three-storey new building BT I school specialist classes on the eastern property:
- 2nd construction phase: Abbr. Existing specialist classes;
- new building of sports hall BT II;
- 3rd construction phase: Abbr. Existing sports hall;
- new three-storey school BT III:
Classes / administration of the teachers' room - follow-up: demolition of existing classroom wing and lunchtime supervision
Manufacture of outdoor facilities
Making fine planum 5600m2 Creating boh piles about 1950lfm Bohpfähle create about 1950lfm foundation beams about 880m3, floor slabs create about 870m3, ceiling tiles and roofs about 3200m3, walls about 900m3, steel quantity about 1000t Foundation beams about 880m3, floor slabs create about 870m3, ceiling tiles and roofs about 3200m3, walls about 900m3, steel quantity about 1000t Masonry work about 250m2 Masonry work about 250m2 Coatings for floor about 250m2 Coatings for floor about 250m2 Coatings for floor about 250m2 Basic line work Basic line work Electrical work in STB total Electrical work in STB total plastering work approx. 100m2 plaster work approx. 100m2 screed work approx. 50m2 screed work approx. 50m2