As part of the façade renovation of the six-storey administration building, the exposed aggregate concrete façade panels will be renewed.
- preparatory actions
- Deliver façade anchor system + install
- Trusses window area + attic supply + install
- Provide thermal insulation of the ventilated façade + fix it (approx. 2,125 m²)
- Installation of horizontal fire barrier + permanent scaffolding anchor
- Manufacture and installation of exposed aggregate concrete façade panels type 1-9 (approx. 1400 pieces)
- Hydrophobization of exposed aggregate concrete façade panels
- Other work
Completion of work and assembly planning + building physics and static verifications: 05.12.2023
Delivery sample plate: 16.01.2024
Execution period (installation façade UK + insulation): 24.06. - 09.08.2024
Ausführungszeitraum (Montage Waschbetonplatten):
15.07. - 23.09.2024