Ventilation and air-conditioning systems for the 1st BA
Brief description of the measure:
In addition to the existing main building, a 3-storey new building for a primary school is to be built on the site of IGS Lindenfeld. The construction project will be carried out in 2 construction phases. The benefit described here concerns the 1.BA. The building will be constructed in solid construction. The ventilation of the classrooms and function rooms is carried out via decentralised façade ventilation units. The ancillary rooms are ventilated and ventilated via central supply and exhaust air systems.
Execution times
Start of work: 21.08.2023
Interim periods:
Rohinstallation 21.08.2023 - 10.11.2023
Installation 13.11.2023 - 26.01.2024
Final assembly 09.04.2024 - 17.06.2024
Acceptance / Commissioning 09.07.2024 - 19.08.2024
Gesamtfertigstellung: 19.08.2024