The subject of the proceedings is structural engineering services in accordance with HOAI 2021 for the realignment and development of the Kirchzarten building yard.
The subject of the proceedings is structural engineering services in accordance with HOAI 2021 for the realignment and development of the Kirchzarten building yard.
The building yard of the municipality of Kirchzarten currently consists of a total of four buildings of different sizes and typologies. The unfavorable positioning of the buildings on the three-sided enclosed site within the industrial park is currently leading to major restrictions in operational processes.
Upgrading the existing buildings does not make sense in terms of energy and economy.
On the basis of the feasibility study prepared by the architectural firm harter + kanzler & partner, the restructuring of the building yard envisages dismantling the existing buildings in sections and realizing the new building in 2 construction phases during ongoing operations, with the following buildings. The urban design must be implemented and the preliminary design concept must be continued in the planning.
Building 1: Administrative and social buildings
Building 2: Workshop Hall
Building 3: Nursery, vehicle and warehouse
Building 4: Covered outdoor area
Construction phase 1a
=============
In construction phase 1a, the administration wing with underground ramp, the courtyard access road and the warehouse are to be built on the street side. For this purpose, the centrally located hall construction must be dismantled in advance. Until the realisation of the further stages, a more difficult access is to be expected due to the whereabouts of the locksmith's workshop building.
To the south, in the area of the existing washing area, the oil separator is to be renewed for its operation. In the further construction phases, the new washing hall and the covered outdoor washing area will be connected to it.
Construction phase 1b
=============
Carpentry and locksmith's shop. The former carpentry hall will be dismantled immediately before the start of the 2nd construction phase. It is temporarily used as a warehouse and vehicle hall.
Construction phase 2
============
Car repair shop and car wash
Planned total costs of the measure (KG 300+400)
===========================================
Construction phase 1a: approx. EUR 2,330 thousand net
Construction phase 1b: approx. EUR 1,130 thousand net
Construction phase 2: approx. EUR 4,750 thousand net
Preliminary timeline
==================
Start of planning phase January 2024 to May 2024 for BA 1a/1b and 2 to LPH 3
LPH 4 – 6 for BA 1a and 1b from June 2024 (building decision)
Submission of building application for BA 1a/1b by July 2024
Start of construction phase BA 1a/1b approx. March 2025
Construction period BA 1a/1b from February 2025 to summer 2026
Start of construction BA 2 still open – to be ordered as an option
The subject of the award procedure is the structural design in service phases 1 to 6 in accordance with §51 HOAI and, if necessary, special services.
The individual service phases are to be commissioned in stages. With the conclusion of the contract for the structural design, the assignment is successively optional as follows:
Work phases 1 to 3 for BA 1a, 1b and 2
Work phases 4 to 6 as well as the engineering control as a special service in work phase 8 for BA 1a and 1b
It has not yet been decided whether BA 2 will be implemented. BA 2 may be commissioned and billed separately at a later date.
There is no legal entitlement to the transfer of all service phases. This applies to BA 1a and BA 1b as well as to BA 2.
The procedure is carried out by way of a negotiated procedure with an upstream public participation competition (pursuant to Section 119 (5) ARC in conjunction with Sections 14 (3) No. 2, 17 (1), 74 VgV).
The two-stage process includes the public participation competition (1st stage: selection phase) and the negotiation phase (2nd stage: submission of tenders and negotiation talks).
In the first stage (participation competition and selection phase), only the application for participation (application) must be submitted together with the required declarations and documents to prove suitability. On the basis of the documents submitted, it is determined which companies meet the eligibility requirements and will be selected for the 2nd stage.
In the second stage (offer and negotiation phase), the companies invited to the negotiation talks are invited to submit an initial non-binding offer and then a revised final offer after the negotiation talks.
The decision on the award of the contract is made on the basis of the negotiation talks and the initial offers and the final offers according to the previously defined award criteria.
The client reserves the right to award the contract or to carry out the evaluation on the basis of the initial offers (§ 17 para. 11 VgV).
The companies not selected in the selection procedure (1st stage) and in the negotiation phase (2nd stage) are informed of the reasons for not being considered.
No costs will be reimbursed for the preparation of applications and offers or participation in the procedure.