A new car park with six levels and a helicopter place on the upper level, approx. 7 000 m² gross. The awarding authority requires extensive use of BIM and industrialisation in order to achieve a very compressed construction period at the construction site. Construction period at the construction site: March-August 2013.
Construction site at the hospital area in Tønsberg. Turnkey contract with a fixed price contract. The turnkey contractor is free to engage engineering designers.
An information meeting will be held for interested contractors Thursday 14.6.2012 (10:00). The meeting will be at Vestfold Hospital, in the Planning and Development Unit's premises, Håkon V gate, Tønsberg, Norway.
NOTE: To register your interest in this notice and obtain any additional information please visit the Doffin Web Site at http://www.doffin.no/Search/Search_Switch.aspx?ID=259667.