The existing outdoor pool in the Salinental valley will be expanded by the new construction of the indoor pool in order to ensure not only the wellness thermal baths but also the offer of the city of Bad Kreuznach in the form of a sports and family pool.
For the new construction, the existing outdoor pool building with supply and changing area and the technical building will be dismantled and replaced by the planned building.
This new building will include the entrance, changing and shower area and integrate the technology for the outdoor pool area. At the same time, structural and technical measures are being taken to sustainably maintain the existing functionality of the outdoor pool and at the same time to increase its attractiveness. In addition, a new children's pool is being built, which can be assigned to both bath areas.
- GFA: 3,950 m
- BRI: 18 867 m
- Water surface of the outdoor pool: 2 300 m
- Water surface of the indoor pool: 539 m
- Subfloor preparation for walls (HDW) approx. 1,385 m
- Clean the subsurface, pool walls, floors, etc. Pool head approx. 1 510 m
- Modeling of the pool head approx. 150 m;
- composite sheet pool head approx. 300 m;
- Polyester fleece compensation u. Drainage layer wall / floor approx. 1 360 m
- PVC pool lining wall / floor 1 360 m
- Channel gratings approx. 150 m;
- PE special turned part for PE-HD pipe sockets approx. 85 pieces;
- Final assembly kit for inflow system approx. 85 pieces