The following earthworks will be carried out:
excavation:
- Storage of excavated material, GW-GW/X - 8,300 m3
- Storage of excavated material, GW-GU - 2,500 m3
Disposal:
- Auelehm Z0 - 2.900 t
Hinterfüllen, Auffülungen:
- Backfill warehouse - 2,230 m3
- Replenishment warehouse - 8,400 m3
The city of Memmingen, Stadtwerke Memmingen, is planning to build a new combined indoor and outdoor swimming pool as a year-round swimming pool.
The new building is to be built on the site of the existing outdoor swimming pool, after demolition of the existing building. The new combined pool includes a 25-meter swimming pool with 8 lanes, a diving board 1 meter / 3 meters, a teaching pool with approx. 12.5 x 10 meters, a course pool with movable floor, a
Toddler pool, as well as other attractions. In the area of the outdoor pool, a 50-meter pool with 6 lanes, a non-swimmer pool with approx. 500 m² with various attractions and a toddler pool with approx. 100 m² are being built. In addition, in addition to a beach volleyball court, a playground and
like, an outbuilding with changing rooms, sanitary facilities and a kiosk was built.
For a detailed description of the earthworks, see the service description.
Scheduled schedule:
Work will begin within 12 working days of receipt of the request, which is expected to be received by week 30/2023.
The service must be completed (ready for acceptance) within 675 working days after the above-mentioned deadline for the start of execution.