The purpose of this procurement is to contract a contractor to execute contract ‘M010 Security Installations’.
The contract includes:
Automatic intruder alarm system, AIA.
Automatic access control system, AAK.
TV monitoring system, TVO.
Object alarm, OA System for monitoring of art objects.
For a more detailed description of this contract's scope, refer to Part B Work Scope and Payment and Part F Drawings.
Optimalisation Process.
After signing of the contract, an optimisation period of approx. 6 months will be executed as part of contract ‘M005 Internal structural works and technical installations’.
The optimalisation period goals:
1. Reduce the risk for the builder and contractor.
2. Provide optimal technical systems.
3. Ensure predictability and rational production.
4. Reduce project costs.
5. Create trust between the builder and contractor, team-building.
Contract ‘M010 Security Installation’, must reckon on participating in parts of this process for the coordination of progress and technical solutions.
Design Phase.
A design phase in two stages for a total length of approx. 6 months shall be carried out for contract ‘M010 Security Installations’ after the contract has been signed:
1. Provisional design.
2. Final design.
The total work basis shall be agreed and determined during this phase.