The project - Kildedal – Rerouting of gas transmission pipeline and new meter and regulator station – Ballerup – Zealand – incl. 16”/DN400, app 2 km pipeline, meter and regulator station area incl. all related work.
The project - Kildedal – Rerouting of gas transmission pipeline and new meter and regulator station.
• Temporary areas for pipe storage, soil storage, access roads, car parking and staff facilities.
• Staff facilities (changing facilities, toilets, meeting and lunch rooms, offices etc.)
• Gas transmission pipeline 16”/DN400, app. 2 km (including excavation free crossings, see below)
o Working belt preparation
o Welding and testing (NDT)
o Pressure test
o Re-establisment of working belt
• Excavation free crossings:
o Horisontal Directional Drilling app. 370 m under protected lake
o Tunneling app. 150 m under railway, main road (4 lanes) and small private road
• Meter and regulator station area with:
o Site preparation and terrain leveling
o Line valve arrangement, distribution valve arrangement and vent stacks
o Pavement and access road
o Fence, gates and plantation belt around the station area
• Re-establisment of all temporary areas.
The Contracting authority will deliver pipes, hot-bends, valves, insulation couplings, marking and measurement posts.