Jewish Academy - new shell construction
Shell of new building
Main services:
04.01- Construction site installation
- construction site equipment and safeguards: 1st
04.02- Main lines
- basic services from DN 100 to DN 150:240 m
- Ditches and refilling them: 200 m3
04.03- in-situ concrete, exposed concrete work
- concrete foundations, base plate, walls, ceilings,
coloured in exposed concrete areas: 1,650 m3
- smooth formwork, walls, ceilings, etc.
50% exposed concrete SB 3, calculated on one side 10,000 m2
- structural steel foundations, base plate, walls, ceilings, etc.
1,650 Ut
- Representative spiral stair flights in exposed concrete
with solid parapet, UG to DG 6 pcs
- Sculptural hall ceiling in exposed concrete 210 m2
- exposed concrete wall base for fence system, outside 200 m
04.04 masonry
- masonry KS 11.5 cm to 17.5 cm 300 m2
04.05 Sealing vapor barriers, insulation
- waterproofing membranes bituminous 550 m2
- perimeter insulation base plate, UG walls 1000 m2
04.06 precast concrete elements
- exposed concrete base outside, including core insulation 200 m2
- prefabricated stair flights in exposed concrete 12 pcs
04.07 steel installations
- composite steel beam h approx. 3 m 20 m
- steel structure hall cantilever 60 m2