Project 20.371AB/1 & WET3025 (GIP O206183B) - Wetteren, collector Molenbeek phase 2
Construction and improvement cycle path along the N462
LOT 2: from the N9 to the border with Sint-Lievens-Houtem
- Breakout of the roads and side strips
- The construction of new roads in the entire project area includes foundation works, bituminous pavements and small-scale materials, concrete linear elements and drainage elements. In the central zone, an elongated traffic platform in concrete will be constructed
- Construction of parking lanes, footpaths and plot accessways in clinker pavement
- Construction of central zone in reuse boulders and mosaic boulders, partly permeable to water (parking church)
- Construction of bicycle paths in asphalt pavement and bike suggestion strips in washed out brown concrete
- Muting existing canals and realizing new ones with culverts for the plot accesses and with weirs for buffering
- Construction of new masonry head walls
- Construction of gravitational pipes 300 to 600 mm in open trench, laying of reinforced concrete tube. DWA is constructed in grèspipes and RWA in concrete pipes, partly in porous concrete and the associated shoring works.
- Extension of the boiled watercourse and placement of 2 head walls in concrete poured on site
- Construction of various structures for the sewerage system: GR25b, GR28, GR29, GR40, GR43, GR47a, GR111, GR112, GR113
- Construction of press pipe
- Construction of 2 buffer basins with associated constructions BU1, BU2, BU3, BU4 and BU5
- Construction of green areas with plantings of trees
- Making home and street column connections
- Maintenance of the works during the guarantee period
- Archaeological Research
Project 20.371AB/1 & WET3025 (GIP O206183B) - Wetteren, collector Molenbeek phase 2
Construction and improvement cycle path along the N462
LOT 2: from the N9 to the border with Sint-Lievens-Houtem
- Breakout of the roads and side strips
- The construction of new roads in the entire project area includes foundation works, bituminous pavements and small-scale materials, concrete linear elements and drainage elements. In the central zone, an elongated traffic platform in concrete will be constructed
- Construction of parking lanes, footpaths and plot accessways in clinker pavement
- Construction of central zone in reuse boulders and mosaic boulders, partly permeable to water (parking church)
- Construction of bicycle paths in asphalt pavement and bike suggestion strips in washed out brown concrete
- Muting existing canals and realizing new ones with culverts for the plot accesses and with weirs for buffering
- Construction of new masonry head walls
- Construction of gravitational pipes 300 to 600 mm in open trench, laying of reinforced concrete tube. DWA is constructed in grèspipes and RWA in concrete pipes, partly in porous concrete and the associated shoring works.
- Extension of the boiled watercourse and placement of 2 head walls in concrete poured on site
- Construction of various structures for the sewerage system: GR25b, GR28, GR29, GR40, GR43, GR47a, GR111, GR112, GR113
- Construction of press pipe
- Construction of 2 buffer basins with associated constructions BU1, BU2, BU3, BU4 and BU5
- Construction of green areas with plantings of trees
- Making home and street column connections
- Maintenance of the works during the guarantee period
- Archaeological Research