The scope of the contract includes contract performance management and multi-industry investor supervision over services, including design works, supplies and construction works commissioned to the General Contractor for design, construction, technical maintenance and demolition of the Polish Pavilion at the World Exhibition EXPO 2020 in Dubai in the United Arab Emirates.
1. The basic scope of the contract includes contract performance management and multi-industry investor supervision over services, including design works, supplies and construction works commissioned to the general contractor as part of the works contract. The basic subject of the contract includes:
1) stage I - management of the contract implementation and multi-disciplinary investor supervision over stage I of the contract for construction works, i.e. designing the Polish Pavilion,
2) stage II - management of the contract implementation and multi-industry investor supervision over stage I of the contract for construction work, i.e. construction of the Polish Pavilion,
3) stage III - management of the contract implementation and multi-disciplinary investor supervision over stage I of the contract for construction works, i.e. technical maintenance of the Polish Pavilion during the Exhibition.
A detailed description of the subject of the basic contract is set out in Annex 1.
2. The awarding entity envisages the award of a contract covered by the option right referred to in art. 34 section 5 of the PPL Act. The subject of the order covered by the option right will be:
1) stage IV - management of the contract implementation and multi-industry investor supervision over stage IV of the contract for construction works, i.e. demolition of the Polish Pavilion (option No. 1),
2) increasing the involvement of members of the investor supervision team over the "minimum involvement" set out in Annex 1 (option 2).
A detailed description of the subject of the contract covered by the option right is set out in Annex 2.
3. The contractor will perform the subject of the contract on the following dates:
1) stage I - from the day of concluding the contract until the general contractor obtains the building permit for the pavilion ("Building Permit" referred to, among others, in chapter 10.5.3 of the document "Self-Build Pavilions Delivery Guide");
2) stage II - from the date of conclusion of the contract until the General Contractor obtains permission to use the pavilion ("Operation Fitness Certificate", referred to in chapter 10.8 of the document "Self-Build Pavilions Delivery Guide")
3) stage III - from the day the pavilion is put into use until 10.4.2021;
4) stage IV - during the implementation by the general contractor of the demolition works of the Pavilion and works related to the restoration of the plot to its original condition in the period from 11.4.2021 to 30.9.2021 (if the Employer exercises the option right, about referred to in Chapter III, section 2, item 1).
Detailed deadlines for the implementation of individual services are specified in the detailed description of the subject of the contract constituting Annex 1.