Worked: 1180-001 Dachabdichtungsarbeiten
Prompt to start execution: vsl. 05.12.2023
Fertigstellung WMP: vsl. 26.01.24
BT Süd Dach dicht: vsl. 15.03.24
BT Nord roof tight: vsl. 29.03.24
BT South Completion: vsl. 23.08.24
BT North Completion: vsl. 06.09.24
Total execution period (order to completion):
vsl. 05.12.2023 – 06.09.2024
For further individual dates, see Form 214 Appendix 1