Hospital Barmherzige Brüder Munich, master planning 1.BA VE 3450 fire protection curtain outside / inside, masonry and. Plastering, painting.
Hospital Barmherzige Brüder Munich, master planning 1.BA VE 3450 fire protection curtain outside / inside, masonry and. Plastering, painting work Scope of services:
- Fire protection curtains outside / inside: 4 units EW-90 curtain outside, area per system approx. 10-12 m
- A total outside: 42 m
- A total inside: 10 m,
- Scaffolding: LK 3, B W09, as facade scaffolding, A = approx. 75 m
- scaffold staircase: 2-gang, H = 15 m,
- Masonry work: 8 m
- Fire wall plastering work: 12 m
- Painting work: 12 m
- Execution times including workshop planning / coordination: start of week 14/2020,
End: 29/2020.