Avenue Eugene Müllendorff - Place d'Arles:
Work to repair the sewage, development of the roads and a friendly space.
Pack 1:
Division 1, 2 and 3: Works for the City of Verviers: Avenue E. Müllendorff - Place D'Arles — Renovation of the wall of Rue des Hougnes
- The selective demolition of hydrocarbon coating in the median;
- Selective demolition of linear and foundation elements;
- The establishment of a geogrid, a geotextile, a sub-foundation and a foundation;
- The laying of two layers of hydrocarbon;
- The implementation of new linear elements;
- The installation of concrete pavers on the street, parking, sidewalk and square;
- The installation of street furniture (benches, trash cans,...)
- Planting trees and flower beds
- Scraping/laying
- Renovation of the retaining wall on Rue des Hougnes
Division 4: Work in... (see market documents)
Work at the expense of the City of Verviers and the SPGEDivision 1, 2 and 3: Works for the City of Verviers: Avenue E. Müllendorff - Place D'Arles — Renovation of the wall of Rue des Hougnes
- The selective demolition of hydrocarbon coating in the median;
- Selective demolition of linear and foundation elements;
- The establishment of a geogrid, a geotextile, a sub-foundation and a foundation;
- The laying of two layers of hydrocarbon;
- The implementation of new linear elements;
- The installation of concrete pavers on the street, parking, sidewalk and square;
- The installation of street furniture (benches, trash cans,...)
- Planting trees and flower beds
- Scraping/laying
- Renovation of the retaining wall on Rue des Hougnes
Division 4: Work at the expense of the SPGE - Pipeline laying
- The necessary excavations for the laying of pipes and visiting rooms;
- The laying of reinforced concrete and PP pipes;
- The installation of visiting rooms;
- The rehabilitation of existing pipes;
- The replacement of existing special connections.
Work for SWDE, RESA, ORES and PROXIMUSDivision 1: Work for Impetrants - Civil Engineering
- Coating demolition/Foundation demolition/Earthmoving/Rocky/Compact/Backfilling/Evacuation/ Hour in management
Division 2: Work in charge of ORES
- Supply and installation of cables + intro + sandblasting + public lighting
Division 3: Work at the expense of RESA
- Supply and installation of pipes + sandblasting
Division 4: Work for SWDE
- Supply and installation of pipes + intro + sandblasting
Division 5: Work for Proximus
- Supply and installation of cables + intro + sandblasting