The old building of the school will be renovated in 2 construction phases: BA2+BA3
The call for tenders applies to both sections:
ca. 935 m2 Metallständerwände
ca. 740 m2 GK-Vorsatzschalen
approx. 650 m2 GK ceilings
ca. 2.770 m2 GK-Lochdecken
ca. 760 m2 Metalldecken
The tender does not include a material price sliding clause.
ca. 935 m2 Metallständerwände
ca. 740 m2 GK-Vorsatzschalen
approx. 650 m2 GK ceilings
ca. 2.770 m2 GK-Lochdecken
ca. 760 m2 Metalldecken
The execution takes place in 2 construction phases:
BA 2: Walls planked on one side: 40th - 43rd week 2022, closing walls: 02nd - 05th week 2023
Ceiling clothing: 09th - 17th week 2023, ceiling teaching kitchens: 44th - 45th week 2022
BA 3: Walls planked on one side: 40th - 43rd week 2023, closing walls: 02nd - 05th week 2024
Ceiling cladding: 09 - 17 kw 2024